Process waste neutralisation project

New design process waste neutralisation system

This project involved the installation of a bespoke process waste neutralisation system for Alexion. Completed within 10 weeks, the scope covered mechanical pipework, instrumentation, builders works, and steel fabrication services, including the creation of stainless steel platforms and walkways.

Key activities and deliverables

  • Installation of a 4000L stainless steel process wastewater vessel
  • Fabrication and installation of stainless steel process waste pipework
  • Installation of PTFE-lined acid and caustic injection pipework
  • Lead coordinator for mechanical and electrical services
  • Set out and forming of builders works, including plinths and floor paint finishes
  • Testing and commissioning of mechanical services and equipment

Let’s Talk

See our contact page for further details, or fill out this form, and we’ll get back to you promptly.

"*" indicates required fields

Name*
This field is for validation purposes and should be left unchanged.
*Required Field.