Scope – Electrical installation services provided as follows: LV & ELV containment systems Process instrumentation General services and fixed equipment supplies Lighting Emergency lighting External...
Start date – February 2023 Finish date – August 2023 Scope – Electrical installation services provided as follows; LV & ELV containment systems Process instrumentation Lighting Emergency...
Scope of Work: The project involved the comprehensive installation of electrical systems in 7 months, including: LV & ELV Containment Systems Lighting & Emergency Lighting External Lighting Fire...
Scope – Electrical Installation services provided as follows: LV & ELV containment to the production equipment LV & ELV power hook ups to production equipment Process Instrumentation Structured...
New design process waste neutralisation system This project involved the installation of a bespoke process waste neutralisation system for Alexion. Completed within 10 weeks, the scope covered mechanical...
This project marks the initial phase of a larger expansion, involving the installation of a new chilled water farm to support cooling systems for the facility. The scope of work includes: Installed a 5...
Being the design trade partner nominated by the client for the entirety of the project’s life cycle, our in-house design engineers played a central role in this project. Overseeing the design process...
In January of 2024, Veolia Water Technologies commissioned the supply and install of a purified water treatment system at their Centre of Excellence facility in Kildare. Rockwell were the main mechanical...